July 18, 2024

Senat Residential Complex Construction Update: May–June 2024

Dear investors, as of July 18, 2024, the following works have been completed:

  • Monolithic works fully completed, roofing installed, masonry work on external, inter-apartment, and interior walls finished.

  • Glazing completed 100%.

  • Screed installation works finished.

  • Plastering works of MZK completed.

  • Installation of heating, water, and sewage pipes in progress.

  • Electrical wiring works ongoing.

  • Fire protection system works in progress.

  • Installation of technical metal doors in MZK and technical rooms ongoing.

  • Acoustic insulation of technical rooms against noise completed.

  • Ventilated facade installation works ongoing: one section completed, second section 60% done.

  • Staircase railing installation works ongoing.

  • Tiling works on open terraces ongoing.

  • Installation of aluminum metal structures in non-residential premises on the 1st and 2nd floors completed.


https://youtu.be/Ak6m1xv1Ohw?si=c-O6wZhFxNem2G6g