May 07, 2025

Senat Residential Complex Construction Update: March–April 2025

Dear buyers of the Senat residential complex, we are pleased to inform you that as of May 6, 2025, the following works have been completed:

  • Monolithic works fully completed, roofing installed, masonry work on external, inter-apartment, and interior walls finished.

  • Glazing completed 100%.

  • Screed installation works finished.

  • Plastering works of MZK completed.

  • Installation of heating, water, and sewage pipes done.

  • Electrical wiring completed.

  • Apartment radiators installed.

  • Fire protection system works in progress.

  • Apartment doors installed.

  • Fire-rated technical doors installed.

  • Acoustic insulation of technical rooms against noise completed.

  • Installation of ventilated facade on two sections finished.

  • Staircase railing installation completed.

  • Finishing works in common areas underway (painting, floor tiling).

  • Lighting installation in common areas ongoing.

  • Tiling works on open terraces completed.

  • Pump station installation completed.

  • Boiler room works ongoing.

  • Installation of aluminum metal structures in non-residential premises on the 1st and 2nd floors finished.

  • External network installation for the complex underway.

  • Landscaping works started.


Senat Residential Complex Construction Update: March–April 2025