September 03, 2024

Senat Residential Complex Construction Update: July–August 2024

As of September 2, 2024, the following works have been completed:

  • Monolithic works fully completed, roofing installed, masonry work on external, inter-apartment, and interior walls finished.

  • Glazing completed 100%.

  • Screed installation works finished.

  • Plastering works of MZK completed.

  • Installation of heating, water, and sewage pipes in progress.

  • Electrical wiring works ongoing.

  • Fire protection system works in progress.

  • Installation of apartment entrance doors underway, 70% completed.

  • Fire-rated technical doors installation completed.

  • Acoustic insulation of technical rooms against noise completed.

  • Ventilated facade installation works ongoing, completed on two sections.

  • Staircase railing installation works ongoing.

  • Finishing works in common areas underway (painting, floor tiling).

  • Tiling works on open terraces ongoing.

  • Pump station installation works ongoing.

  • Installation of aluminum metal structures in non-residential premises on the 1st and 2nd floors finished.

Senat Residential Complex Construction Update: July–August 2024