Construction progress of the Senat residential complex, October 2025
As of November 5, 2025, the following has been completed:
Monolithic work has been completed in full, roofing has been installed, and masonry work on exterior, inter-apartment, and interior walls has been completed.
Glazing has been completed 100%.
Work on installing the screed has been completed.
Plastering of the MZK has been completed.
Heating, water, and sewage pipes have been laid.
Electrical wiring has been completed.
Apartment radiators have been installed.
Work on the installation of fire protection systems has been completed.
The installation of apartment doors has been completed.
The installation of fire-resistant technical doors has been completed.
Acoustic protection of technical rooms from noise has been completed.
Work on the installation of a ventilated facade on two sections has been completed.
Work on the installation of staircase fencing has been completed.
Work on the finishing of common areas (painting, laying floor tiles) has been completed.
Lighting has been installed in common areas.
Fire protection systems have been installed.
Tiling work on open terraces has been completed.
Pumping station installation work has been completed.
Electrical panel installation work has been completed.
Work on the installation of the boiler room has been completed, and commissioning work is underway.
Work on the installation of aluminum metal structures in non-residential premises on the 1st and 2nd floors has been completed.
Work on the installation of external networks for the complex is underway.
Installation of a gas pipeline for connecting the boiler room has been completed.
Work is underway to improve the territory
Construction of a transformer substation is actively underway
Construction progress of the Senat residential complex, September 2025