The main construction work on the Senat residential complex has been completed, and the team is now focusing on landscaping the grounds.

As of July 2026:

✔️ The building’s structural frame has been erected, and facade cladding is nearing completion

✔️ In the apartments, floor screeds are complete, radiators have been installed, and

internal utility systems have been laid

✔️ Common areas and open terraces have been brought to completion

✔️ The boiler room, electrical room, and pump station have been installed, and the equipment

is ready to be commissioned

✔️ Final finishing work is underway in the entrance area