January 12, 2026

Construction progress of the Senat residential complex, December 2025

We share the current status of the works:

✔️ Monolithic works, roof installation and

laying of external, inter-apartment and inter-room walls have been fully completed.

✔️ Glazing of the house has been completed by 100%.

✔️ Work on arranging floor screed has been completed.

✔️ Plastering works in common areas have been completed.

✔️ Heating, water supply and sewage pipelines have been laid.

✔️ Electrical networks have been laid.

✔️ Apartment radiators have been installed.

✔️ Fire protection systems have been installed.

✔️ Installation of apartment and fire protection technical doors has been completed.

✔️ Acoustic protection of technical premises from noise has been completed.

✔️ Installation of a ventilated facade in two sections has been completed.

✔️ Staircase fencing is ready.

✔️ The finishing of common areas has been completed (painting and tiling of floors).

✔️ Lighting has been installed in common areas.

✔️ Tiling of open terraces has been completed.

✔️ Work on the arrangement of the pump and electrical switchboard has been completed.

✔️ The arrangement of the boiler room has been completed, commissioning work is currently underway.

✔️ Aluminum metal structures of non-residential premises on the 1st–2nd floors have been installed.

✔️ The installation of a gas pipeline for connecting the boiler room has been completed.

✔️ Work on the arrangement of external networks of the complex is ongoing.

✔️ Landscaping continues.

✔️ Construction of a transformer substation (TP) is actively underway.

Construction is confidently moving according to schedule. We will continue to inform you about all key stages of the development of the Senat residential complex 🤍

Construction progress of the Senat residential complex, December 2025